The Docket

Every decision in the record, its status at a glance, and the next date that matters. Dashed magenta means nothing is binding yet.

DecisionStatusWhat comes next
IHMC Healthspan Center
Triumph #233
Executed · mid-performancePM#1 (expend ≥$58.5M research) due 2036-12-31; annual Oct-31 reports S-23
American Magic
Triumph #315
Built · pivoted to defenseLease jobs deadline ≈ Jan 2029 if the DBO tracks the 2026-01-07 opening (inferred; DBO certificate wanted), else 2029-12-31. Triumph 170-job metrics due 2029. SailGP base opens Sept 2026 (trigger T3d). S-29 S-07
UWF WAVE
Triumph #330
Term sheet executed (non-binding until GAA)175 certificates + ≥$9.95M extramural due 2034-12-31 S-18
Birdon / Project Maeve
Triumph #367
PRE-EXECUTION — nothing binding yetGAA target ~Aug 2026, then a 25-yr lease — both need City Council approval. Jobs ramp-up deadline 2035-12-31 if executed as drafted. S-14 S-07 S-11
HPMCE Dock Complex
Bid 26-029 · FSTED
Awarded · under construction180-day landside completion clock from notice to proceed ($500/day penalty) S-16 S-17

Machine-readable: data/docket.json.