How to read solid = documented fact dashed = reported / inferred / proposed magenta = monitored question

UWF WAVE

Triumph #330 · 2024
Bottom line — every sentence assembled from the cited record
Promised

A workforce "magnet" built explicitly around American Magic's arrival — $3.3M of a $16.7M project, in the beneficiary's own framing.

self-reported / promotionalS-19 S-31
Binding

By 2034: ≥175 marine-composites certificates ($18,947 clawback per certificate short) and ≥$9.95M in extramural funding obtained and spent (23.8% of any shortfall). Term sheet executed 2024-12-18 — yet non-binding until a definitive grant agreement.

What changed

Nothing yet, honestly: outcomes are too early to assess, and the definitive grant agreement is not in the record. That absence is the open question this page holds.

The full record layer — every claim cited, statuses verbatim:

The deal

Term sheet executed 2024-12-18 by Triumph's Chairman and UWF's President (DocuSign): up to $3,315,600 of a $16,655,600 project — the grant is ~20% of the project. Note: executed, yet its own boilerplate disclaims binding effect until a definitive GAA.

verified S-18record/decisions/uwf-wave-330/uwf-wave-extraction-run-01.md

Two binding metrics by 2034-12-31: ≥175 Net New Certificates (ABYC Marine Composites), clawback $18,947 per certificate short; and obtain-and-spend ≥$9,946,800 in extramural funding, clawback 23.8% of the shortfall. The basis of the 23.8% figure is not derivable from the face amounts — recorded as stated, flagged.

verified S-18record/decisions/uwf-wave-330/uwf-wave-extraction-run-01.md

The catalyst chain, on paper

WAVE's proposal builds the case on American Magic's arrival — "has attracted many WAVE related industries" — and names the partnership in its application. This is the cluster narrative forming in a primary document (2024), before Triumph's 2026 reframing. Because the claim is asserted by its beneficiary, it is rendered here as a claimed relationship, never as neutral fact.

reported self-reported / promotional S-19 S-31record/decisions/uwf-wave-330/uwf-wave-extraction-run-01.md

Open questions

The definitive GAA for #330 — the binding instrument beyond the term sheet — is not in the record; actual certificate and extramural progress is too early to assess.

monitored S-18record/decisions/uwf-wave-330/uwf-wave-extraction-run-01.md

Relationships in the graph

From data/graph.json — every edge carries its epistemic status and source citations.

Sources behind this page's runs